Planning production in Excel: how far does it really hold?
Most mid-market manufacturers still plan production in Excel, and they have good reasons to hold on to their spreadsheet. What it does well, where it breaks, and the signals that say the threshold has been crossed.
Key takeaway
Most mid-market manufacturers still plan production in a spreadsheet, usually for sound reasons rather than technological lag. Excel does some things no specialized software matches, but it breaks on finite capacity with dependencies between stations, on multi-site consolidation, and on version control and dependence on one person.
Why most mid-market manufacturers still plan in a spreadsheet
When you ask a mid-market manufacturer's planner where their production plan lives, the answer is most often a workbook, with a tab per week or per line, and a macro only they dare to rerun. This choice has little to do with technological lag: it results from a series of reasonable decisions. The ERP's planning module was tried, then abandoned because it reasoned at infinite capacity or imposed a routing logic the plant did not keep up to date. APS have long been sold, priced and deployed for groups, with projects counted in years that a company of three hundred people could not carry. So the planner built their own tool, year after year, coding into it everything the plant knows about itself, and that file works, which remains the best reason in the world not to replace it. I do not know many manufacturers who planned in a spreadsheet out of laziness; they did it because nothing else fit their size.
What Excel does very well in production planning
The spreadsheet must be credited with qualities no specialized software matches on its turf. It absorbs a new constraint in one column, where an APS requires configuration and sometimes development; it lets itself be understood cell by cell, so the planner knows exactly why the file proposes 400 pieces rather than 350. It costs nothing more than the office license already paid, and it lets you test a hypothesis in ten minutes, by duplicating the tab and changing three values. This ownership has a value people underestimate, because a planner who built their workbook often knows their plant better than an APS user who endures a model built by an integrator. On a single site, with a few dozen active items, stable routings and a readable order book, a production plan in a spreadsheet can remain the right answer for years, and there is no shame in saying so.
Where it breaks: finite capacity and multi-site
The spreadsheet knows how to calculate requirements; it does not know, by itself, that a machine is full. To teach it, someone built a load tab that adds up the hours per station and per week, and that tab does its job as long as the stations are independent. It stops doing it as soon as one station's load depends on the sequence on the previous one, that two items compete for the same tooling or that a bottleneck dictates the throughput of the whole line, because these dependencies require an iterative calculation that formulas do not carry. Planning then becomes optimistic without anyone seeing it, and the overload is discovered on the floor, in week 38, when it is too late to smooth. Multi-site finishes complicating the picture: two plants, two workbooks, two ways of counting capacity, and a consolidation done by hand on Friday that allows neither arbitrating a load transfer between sites nor knowing which of the two is really the most loaded. At that stage, the file no longer plans, it records what each person decided on their own side.
Where it also breaks: versions and the person
The second family of limits concerns less the calculation than the circulation of the file. The sales rep has their copy, where they entered the order promised to their customer; production has its own, where that order does not yet exist; procurement works on the version emailed Friday evening. Monday's planning meeting becomes a reconciliation meeting, where most of the time is spent finding out which file is authoritative before anything can be decided. The real plan ends up being the one that stayed in the head of the person who built the workbook. That person is the third point of fragility, and the most serious: when they are away, there is no production schedule that week. Nobody else understands the hidden tabs, the hard-coded cells and the exceptions the file has accumulated over ten years. A plant that depends on a workbook actually depends on an employee, and that dependency appears in no dashboard as long as everything goes well.
The signals that say the threshold has been crossed
The move from the spreadsheet to a tool is decided on symptoms observable at home, more reliably than on a vendor's demo. The weekly plan update takes more than a day, while it is already stale by Tuesday. The dates promised to sales come out of the planner's experience rather than the file, because nobody trusts the file anymore. A station overload is discovered on the floor and never in the plan, and a late component forces you to rebuild the workbook by hand, which takes half a day during which the shop moves ahead with no instructions. Two sites compete for the same capacity without anyone able to settle it on figures, and the file contains tabs no one dares to change anymore. When three of these signals pile up, the spreadsheet already costs more than it returns, even if that cost appears on no budget line: it is paid in overtime decided too late, in express freight and in runs launched for a customer who could have waited.
What a tool changes, and the decision it does not make
A production planning software brings four things the workbook cannot offer, whatever the quality of its author. First a finite capacity calculated station by station with the dependencies between them, then a single version of the plan that sales, production and procurement read at the same time. Then replanning in minutes when a component slips, and finally a trace of what was changed, by whom and why. It gives the planner back the time spent consolidating, to reinvest in analysis, which is already a good reason to switch. What it does not do deserves to be said just as clearly, because disappointed projects almost always come from a misplaced expectation. The plan produced by the tool will be wrong too, in proportions close to those of the spreadsheet, since it rests on the same forecasts and the same supplier lead times. The gap between the plan and reality is part of the ordinary running of a plant, and two well-equipped sites differ mostly in what they do in the hours following that gap. Deciding which customer waits, which run you cut, which extra cost you accept, remains a human decision, and a well-chosen tool does not remove it: it makes it faster, because it starts from an accurate plan, and more lucid, because it can finally be quantified. The spreadsheet long hid the cost of these trade-offs, between 4 and 12 margin points a year for poorly absorbed disruptions according to what we measure, and a tool's first merit is to make it visible.
This article starts from a conviction: the perfect forecast doesn't exist, what matters is the decision that follows.
- Why most mid-market manufacturers still plan in a spreadsheet
- What Excel does very well in production planning
- Where it breaks: finite capacity and multi-site
- Where it also breaks: versions and the person
- The signals that say the threshold has been crossed
- What a tool changes, and the decision it does not make
Clevizio
Clevizio is the decision layer that plugs into your existing tools: it detects disruptions, simulates your options and keeps a record of every trade-off. See how the decision copilot works.
Frequently asked questions
Can you plan production in Excel?
Yes, and many mid-market companies do it correctly for years. The spreadsheet suits a single site, with stable items and routings and stations that depend little on one another. It shows its limits as soon as finite capacity has to be calculated with dependencies between stations, several sites share a load, or several versions of the file circulate between sales, production and procurement.
When should you stop planning production in Excel?
When updating the plan costs more than the plan returns. The most reliable signals are a weekly update that exceeds a day, dates promised from experience rather than the file, overloads discovered on the floor, manual replanning at every late component and a file only one person knows how to run. Three of these signals together are usually enough to justify the change.
What should replace Excel for production planning?
The ERP's planning module, an APS or a scheduler, depending on where the spreadsheet breaks. The ERP module is enough if the constraints are simple, the APS is called for if finite capacity and multi-site are at stake, the scheduler if the pain is in the shop sequence. In every case, the spreadsheet keeps a role for one-off analysis, and the decision against disruptions, which customer to delay and at what cost, remains to be organized separately, with figures in euros.
Finally put a number on what disruptions cost you every year.
Let's start by estimating what your disruptions really cost you. It's free, it takes 30 minutes, and you leave with a figure nobody in your company knows today.