Simulate the impact of material prices on your costs

Simulating the impact of price swings on supply chain costs takes four inputs: bill of materials, material share, indexation and stock. The method and a worked example.

Mansour NiangBy Mansour Niang, CEO & co-founder, Clevizio·Published October 18, 2026·7 min read

Key takeaway

Simulating the impact of a raw material price increase means multiplying, component by component, the price change by its weight in the cost of goods, then shifting the effect according to the stock bought at the old price and the indexation clauses. The simulation yields a unit cost, a date when the increase lands and a margin to defend.

Why simulate an increase rather than record it?

Simulating the impact of a price swing lets you decide before the increase lands in your accounts, whereas recording it means discovering it in the standard cost variance of the following month, when customer orders have already been taken at the old price. Financial control sees that variance, but too late and at too aggregated a level to say which products are affected and from when. Purchasing knows the increase announced by the supplier, without always knowing which bills of materials the material enters or how much weight it carries in the cost of goods. The simulation links these two kinds of knowledge that rarely live in the same file. It answers the three questions a leadership team asks at every announced increase: how much it costs per year, on which products, and from which date. With these three answers, the discussion leaves the debate about market trends and becomes a choice between costed options, which saves several weeks on a decision to pass on a price or to hedge.

Step 1: start from the bill of materials and the material share

The basis of the simulation is the exploded bill of materials of each finished product, taken down to the purchased materials, with for each component its quantity and its current unit cost. From this you derive the material share, that is the weight of each material in the cost of goods, expressed in euros and then as a percentage. This calculation often holds a surprise, because a material marginal in volume can weigh heavily in value, and a spectacular increase on a secondary material sometimes matters less than a modest increase on the steel or copper that form the body of the product. You also have to trace the indirect consumption: energy in the conversion cost, packaging, inbound transport whose price follows diesel. For a mid-market company managing a few thousand items, there is no point in modeling everything on the first pass. The twenty products carrying the largest share of revenue and the five most volatile materials are enough for a first reliable reading, which you then extend if the gaps justify it.

Worked example: a steel increase on a 100-euro part

Take a mechanical part whose cost of goods is 100 euros, sold at 20,000 units a year, and simulate a scenario where steel rises 20%, aluminum 10%, electronics 5%, cardboard 15% and inbound transport 8%. The impact is calculated line by line by multiplying the component cost by the simulated change, then adding up. In this example, the unit cost goes from 100 to 111.87 euros, an increase of 11.9% even though no material rose more than 20%, and the gross annual impact reaches 237,400 euros. It is this figure that must land on the committee's table, together with the breakdown that shows steel alone carries three quarters of the increase and therefore deserves the largest share of the negotiating effort.

Cost itemCurrent cost per partSimulated changeImpact per part
Steel (sheet)45.00 €+20%+9.00 €
Aluminum (profiles)12.00 €+10%+1.20 €
Electronic components18.00 €+5%+0.90 €
Cardboard packaging3.00 €+15%+0.45 €
Inbound transport4.00 €+8%+0.32 €
Labor and overhead18.00 €0%0.00 €
Total100.00 €+11.9%+11.87 €

Step 2: date the impact with stock and indexation

The simulated unit cost does not yet say when the increase will hit your margin, and this is where most simulations stop too soon. On the upstream side, the stock in place and the orders already confirmed at the old price cushion the shock. With two months of steel coverage, the increase only enters the cost of the parts produced in the third month, provided the valuation follows the reality of purchases. Supplier contracts indexed on a published index, with a quarterly revision, also move the arrival date. On the downstream side, the same mechanics work in your favor or against you. If half your volume is sold under contract with an indexation clause and a three-month lag, you recover part of the increase, but later than you bear it. Back to the example: with two months of stock at the old price and customer indexation on half the volume, the net loss of the first year falls to around 129,000 euros, that is ten months of increase borne, seven of them half offset. The dip concentrates in months three to five, and the simulation must produce this curve over time in addition to the annual total.

The mistakes that skew a price simulation

The first mistake is to simulate on the year's standard cost instead of the latest actual purchase price, which underestimates the impact when a first increase has already gone through without the standards being revised. The second forgets second-order effects: a steel increase also shows up, a few months later, in the price of sub-assemblies bought from suppliers who use it themselves, and a simulation limited to directly purchased materials does not see it. The third treats all items the same way, when volumes, customer contracts and price sensitivity differ sharply from one range to another. The fourth ignores currency, when a material quoted in dollars moves through both its price and the euro-dollar parity. The last, more discreet, lies in stock valuation: depending on the method chosen, weighted average cost or first in first out, the increase appears in the accounts at different dates. Financial control must therefore validate the assumption before the figures circulate. None of these mistakes makes the simulation useless, but each can shift the result by several points.

What decisions to take once the impact is costed?

Once the impact is costed and dated, three families of decisions open up, and the simulation serves precisely to compare them on the same basis. Hedging means securing the price by an advance purchase before the increase, a fixed-price contract over six months or a financial hedge on quoted materials. Each has a stock cost or a premium to set against the expected gain. Passing on targets the customer, through a general price increase, an indexation clause negotiated at renewals, or a targeted pass-on only on products whose material share exceeds a threshold, which protects the ranges where competition is fiercest. Substitution acts on the product itself: an alternative material, a thickness reviewed with the engineering office, a second supplier in a less exposed area, at the cost of a qualification that often takes several months. In practice, the right answer combines the three, with a short-term hedge that buys the time needed for substitution and a pass-on that protects the margin during the transition.

The useful scenario is the one you rerun in an hour

The temptation is to build a very complete model once a year, at budget time, then shelve it until the following year. Material prices, however, do not move at the pace of the budget: a supplier announcement, an index move or a customs decision can change the picture on a Tuesday. The value of a simulation then lies in the speed at which you rerun it with the new parameters. Nobody forecasts the price of steel six months out with certainty, and chasing the right forecast consumes the time the decision will lack. Better to have three scenarios ready, a moderate increase, a strong increase and a decrease, each with thresholds that trigger a predecided action. The day the index crosses the threshold, the trade-off has already been prepared, costed and validated by leadership, and all that is left is to execute it instead of debating it. Keeping a record of these choices, with the assumptions that justified them, also lets you measure after the fact what each decision actually returned.

In short

Simulate the impact of material prices on your costs

  • Why simulate an increase rather than record it?
  • Step 1: start from the bill of materials and the material share
  • Worked example: a steel increase on a 100-euro part
  • Step 2: date the impact with stock and indexation
  • The mistakes that skew a price simulation
  • What decisions to take once the impact is costed?
  • The useful scenario is the one you rerun in an hour

Clevizio

Clevizio is the decision layer that plugs into your existing tools: it detects disruptions, simulates your options and keeps a record of every trade-off. See how the decision copilot works.

Mansour Niang

Mansour Niang

CEO & co-founder, Clevizio

A question about your disruptions? Book 30 minutes with me to estimate what they really cost you, with no commitment.

Frequently asked questions

How to calculate the impact of a material price increase on the cost of goods?

You multiply the cost of each material in the product by its percentage increase, then add up across all affected components. The total divided by the initial cost of goods gives the increase as a percentage.

What is a product's material share?

The material share is the weight of the purchased materials in a product's cost of goods, in euros or as a percentage. It indicates the product's sensitivity to price swings in its components.

Should the whole material increase be passed on to the customer?

Not systematically: the pass-on is decided product by product, according to the material share, the competition and the contracts in force. A targeted pass-on often protects the overall margin better than a uniform increase.

Does stock bought at the old price protect against the increase?

Yes, but only for the length of its coverage and if the valuation follows the real purchase cost. It shifts the increase without canceling it, which leaves time to decide.