Order promising: ATP, CTP and a reliable delivery date
Order promising means giving the customer a deliverable date, relying on ATP and CTP rather than on a standard lead time. Formulas, a worked example and what breaks the promise.
Key takeaway
Order promising is the method that sets a customer a deliverable date by checking what remains promisable. ATP (available-to-promise) looks at stock and production already planned, CTP (capable-to-promise) also questions capacity and components. A promise that is right at the start must then be revised when a disruption occurs.
What is order promising?
Order promising is the process that determines, at the moment an order arrives, the date and quantity the company can commit to deliver. It is also called the order promise or customer promise, and most industrial ERPs offer an availability check that is its simplest form. The principle looks obvious, but it runs into a stubborn habit. In many mid-market companies, the date entered on the order is a standard lead time taken from the item record, or the date the customer asked for, because order management has neither the time nor the tool to check. The promise is then an optimistic assumption no one has verified, and customer lateness starts at data entry. Order promising worthy of the name answers two questions in order: do I already have what I need to serve this order in what is in stock or planned, and if not, can I produce it in time. The first question is that of ATP, the second that of CTP.
ATP: promising on what is already there or already planned
ATP, for available-to-promise, is the quantity of an item not yet committed to any order and that can therefore be promised on a given date. It is calculated from three elements: available stock, planned receipts from the master production schedule or supplier deliveries, and customer orders already promised. The basic formula is as follows: ATP for the period equals available stock plus planned receipts for the period, minus the orders already promised up to the next planned receipt. A distinction is made between discrete ATP, calculated period by period, and cumulative ATP, which adds up what remains promisable week after week and indicates what can be promised at the latest on each date. ATP has a rare virtue: it prevents promising the same unit twice, which already removes a good part of the lateness created at data entry. Its limit is symmetrical, since it only sees what has been planned and ignores the capacity that could still be mobilized.
Worked example: promising 100 units
Take a finished item with 120 units in stock at the start of week 1, two batches of 200 units planned in weeks 2 and 4, and orders already promised of 80, 150, 30 and 60 units over the four weeks. In week 1, ATP is 120 minus 80, so 40 units, since the next receipt arrives in week 2. In week 2, it is 200 minus the 180 units promised in weeks 2 and 3, so 20, and cumulative ATP reaches 60. In week 4, the second batch leaves 140 units free, and cumulative ATP rises to 200. A customer calls for 100 units in week 2: that week's cumulative ATP offers only 60. Order management has three honest options, deliver 60 in week 2 and 40 in week 4, deliver the 100 in week 4, or ask planning for a CTP to find out whether 40 extra units can come out earlier. The worst option, the one most often taken for lack of a calculation, is to promise 100 units in week 2 and discover the shortfall on shipping day, taking along the way units already promised to another customer.
| Week | Planned production | Orders already promised | Cumulative ATP |
|---|---|---|---|
| Week 1 (stock of 120) | 0 | 80 | 40 |
| Week 2 | 200 | 150 | 60 |
| Week 3 | 0 | 30 | 60 |
| Week 4 | 200 | 60 | 200 |
What is the difference between ATP and CTP?
ATP answers with what is already planned, CTP answers with what could still be produced. Capable-to-promise takes over when ATP is not enough: it checks whether the capacity of the bottleneck resources and the availability of components allow adding production before the desired date. In our example, if the workshop has 40 units of free capacity in week 3 and the components are in stock or deliverable in time, CTP allows promising the 100 units in week 3 rather than week 4. CTP is more demanding than ATP, because it assumes reliable capacity data, up-to-date routings and a view of supplies, which an APS generally provides more than an ERP alone. It also has a side effect people forget: every CTP promise consumes capacity, so it reduces the workshop's room to absorb a breakdown or an emergency. A company that promises everything in CTP saturates its plan and turns every hazard into lateness, hence the value of keeping a share of capacity unpromised.
Allocating ATP between customers and channels
An ATP calculated on a first-come, first-served basis has a flaw sales leadership knows well: the small customer who orders early consumes the availability the strategic key account was counting on for its order the following week. Companies that serve several segments therefore put in place an allocation, sometimes called allocated ATP, which reserves a share of the promisable quantity for each channel, key customer or region, generally from the plan validated in S&OP. An order first consumes its segment's allocation, then, according to written rules, the unreserved share or that of a lower-priority segment. Allocation protects contractual commitments and high-margin customers, but it has a cost: a quantity reserved and not consumed can sit idle while another customer waits. You therefore have to set a date beyond which unused allocations are released, and review their breakdown at each planning cycle. Without this discipline, allocation becomes a form of hidden stock no one dares release, and real availability degrades while physical stock stays high.
Why promises degrade after data entry
A date cleanly calculated in ATP or CTP remains a snapshot taken at the moment of the order. By the next day, the component supplier announces a week's delay, a machine breaks down, a batch goes to quality control, a strategic customer brings its order forward, and the promised date becomes wrong without anyone touching it. This is the mechanism by which a late order book forms, and it is why a good initial calculation is not enough to protect the service rate. The problem is not so much the recalculation, which any tool can do, as the propagation: which promises are affected by this supplier delay, which can still be met by reallocating stock, which customers to warn and in what order. Most organizations discover these consequences as they go, order by order, often when the customer calls to ask where their delivery stands.
Re-promising at the right moment rather than promising perfectly
No ATP calculation will hold against every hazard, and seeking the perfect promise amounts to seeking the perfect forecast, two exercises that run into the same industrial reality. What sets a supply chain apart as reliable in its customers' eyes is the speed at which it re-promises when the situation changes. It means detecting on the day that a disruption affects existing promises, pricing what each option costs, reallocating, expediting, splitting or shifting, then informing the customer before they discover the lateness. A customer warned ten days ahead with a credible new date forgives far more easily than a customer who learns it at the dock. This assumes a written priority rule, which says which orders to protect when the resource runs short, and a person who settles the out-of-rule cases within the day. ATP and CTP give the right date at the start, the quality of the decision taken after the disruption decides whether that date will be met or renegotiated in time.
This article starts from a conviction: the perfect forecast doesn't exist, what matters is the decision that follows.
- What is order promising?
- ATP: promising on what is already there or already planned
- Worked example: promising 100 units
- What is the difference between ATP and CTP?
- Allocating ATP between customers and channels
- Why promises degrade after data entry
- Re-promising at the right moment rather than promising perfectly
Clevizio
Clevizio is the decision layer that plugs into your existing tools: it detects disruptions, simulates your options and keeps a record of every trade-off. See how the decision copilot works.
Frequently asked questions
What is ATP in the supply chain?
ATP (available-to-promise) is the quantity of stock or planned production not yet promised to any customer. It is calculated by subtracting the orders already committed from the stock and planned receipts, and serves to promise a date without committing the same unit twice.
What is the difference between ATP and CTP?
ATP promises on stock and production already planned, CTP also checks capacity and components to produce more. CTP steps in when ATP does not cover the demand, but it consumes capacity and reduces the room to handle hazards.
How do you calculate cumulative ATP?
Cumulative ATP adds up, week after week, the quantities remaining promisable after deducting the committed orders. With 40 units free in week 1 and 20 in week 2, the cumulative ATP of week 2 is 60 units.
What is re-promising?
Re-promising means recalculating and announcing a new date when a disruption makes the initial promise untenable. It is effective if it happens early, with a priority rule between customers and proactive communication.