MRP and net requirements calculation: definition and how it works
MRP turns a production schedule into dated component requirements: how net requirements calculation works. What it assumes, and why it is no longer enough when reality drifts.
Key takeaway
MRP (Material Requirements Planning), or net requirements calculation, turns the master production schedule into dated purchase and production orders. It explodes the bills of materials, deducts on-hand stock and open orders from the gross requirement, then offsets by the lead times. It assumes infinite capacity, accurate data and a reliable forecast.
What is MRP?
MRP stands for Material Requirements Planning. In French it is called net requirements calculation, or CBN: it is the same mechanism. MRP answers a question that is simple and vital for any manufacturer: to make what I have planned to make, which components do I need, in what quantity and by what date? Present in almost every industrial ERP, it is the silent engine that turns a master production schedule into dated purchase and production orders.
How does net requirements calculation work?
The calculation runs a cascade mechanism. It starts from the master production schedule, what we want to produce and when. It then explodes the bills of materials: each finished product is broken down into subassemblies and then into components, level by level. For each component, it computes the gross requirement, then the net requirement by deducting the available stock and the orders already open. Finally, it positions the orders in time by offsetting them along the lead times: if a component takes six weeks to arrive and production starts in week 20, the order must go out in week 14. The result is a complete schedule of proposed orders.
What are the limits of MRP?
MRP is rigorous, but it rests on assumptions that are rarely discussed. It assumes infinite capacity: it computes requirements as if machines and labor were always available, leaving it to the planner or an APS to check feasibility. It assumes accurate data: up-to-date bills of materials, exact stock, reliable supplier lead times; every gap between the data and reality produces wrong orders. And above all, it assumes that the master schedule, and so the forecast, is correct. MRP never questions its inputs, it runs them.
When reality drifts, MRP recalculates, it does not decide
Faced with an unexpected event, a late supplier, an urgent order, a wrong stock, MRP's response is to recalculate at the next cycle and regenerate orders. That recalculation is necessary but it does not settle the question of the moment: do we rescue this customer at the expense of that one, pay for expedited freight, push back a production order? MRP proposes a new mechanism, it does not compare the options or their cost. A flawless requirements calculation does not make up for a forecast that, by nature, will end up being wrong: between two calculation cycles, there are decisions to make, and they are often worth more than the calculation itself. It is that decision layer, above MRP and the ERP, that makes the difference when the plan breaks.
This article starts from a conviction: the perfect forecast doesn't exist, what matters is the decision that follows.
- What is MRP?
- How does net requirements calculation work?
- What are the limits of MRP?
- When reality drifts, MRP recalculates, it does not decide
Clevizio
Clevizio is the decision layer that plugs into your existing tools: it detects disruptions, simulates your options and keeps a record of every trade-off. See how the decision copilot works.
Frequently asked questions
What does MRP mean?
Material Requirements Planning, or net requirements calculation (CBN) in French. It is the mechanism that turns a production schedule into dated component requirements, by exploding the bills of materials and deducting the available stock.
What is the difference between MRP and ERP?
MRP is a calculation function, the ERP is the management system that hosts it. Most industrial ERPs embed an MRP engine. The ERP records and executes all of the company's transactions; MRP is the building block that computes the component requirements.
What are the limits of MRP?
Three strong assumptions: capacity assumed infinite, data assumed accurate, forecast assumed reliable. And one structural limit: faced with an unexpected event, MRP recalculates at the next cycle but does not compare the options or price their costs. It calculates, it does not decide.